Emergency hospital Berlin - Helipad

Parking level (2001-2002)

A separate parking level was planned and constructed in addition to the existing helipad. This created a place for an additional helicopter to land. GTB rendered all services for building technology in equipment group 1 - gas, water, sewage, and fire extinguishing technology, as well as equipment group 3 - electrical technology. The structure planning rendered by GTB included a precise examination of the existing situation to include unplanned additional loads, as well as calculation and design of the steel construction for the parking level.

Architect / ordering party

SEHW Architekten

Builder

Trägerverein Unfallkrankenhaus Berlin UKB with berufsgenossenschaftlicher Unfallklinik e.V.

Projektleistungen

Planning services

Technical equipment EG 1, 3

  • Basic assessment
  • Preliminary planning
  • Design planning
  • License planning
  • Execution planning
  • Preparation for tendering
  • Participation in tendering
  • Object monitoring

Structure planning

  • Basic assessment
  • Preliminary planning
  • Design planning
  • License planning
  • Execution planning
  • Preparation for tendering

Project parameters

Building sum TE:
EUR 800,000
Planning
start: 2001
Completion: 2002