Pharmaceuticals factory Magdeburg-Osterweddingen (1997 - 1999)

Technical equipment of a factory for the manufacturing of liquids and solids

  • Ventilation, air conditioning, and instrumentation and control technology with documented pressure level control and extreme dampness requirements for 2,400 m² of gross clean room area (production area with clean room classes D and E in accordance with GMP)
  • Generation and distribution of the following process media: Aqua purificata (hot storage in circulating system with UV treatment),
    high-pressure air, heating steam, cooling water, process exhaust and dedusting

  • Sanitary, heating, ventilation, cooling, and high-voltage and low-voltage electrical equipment for the other area: laboratory and staff rooms, workshops (840 m² gross floor area)

  • Offices with dining room and cafeteria (1,475 m² gross floor area)
  • High-rack storage area with scales and logistics (2,200 m² gross floor area)

  • Generation and distribution of heating water and cold water for cooling purposes; high-voltage transformers

Builder

esparma GmbH Magdeburg

Client

ITECS GmbH

Projektleistungen

Planning services

Technical equipment EG 1-3

  • Design planning
  • License planning
  • Preparation for tendering
  • Participation in tendering
  • Object monitoring

Project parameters

Gross floor area:
6,915 m²
Building sum
TE: EUR 2.6 million
Planning
start: 1997
Completion: 1999